Newsletter Vol.3 June 2025

Newsletter Vol. 3 June 2025 | Welcome Home

BE PART OF STRATHMORE PARK SUBDIVISON - Stage 1 selling now!

Strathmore Park is a vibrant, community-driven haven coming soon to the heart of New Zealand’s timber town – Tokoroa. With a commitment to quality, affordability and connection, this new residential subdivision redefines modern living in South Waikato. Home & Land Packages available now from $550,000.

The Strathmore Park subdivision, Tokoroa, will work exclusively with preferred Building Partners, to ensure variety, quality, consistency and fit with overall development vision. You can select a Home & Land Package from a building partner direct, or select your preferred section direct from our Sales Team – then discuss design and build options with your preferred Building Partner, when you are ready to create your new home.

As you can see from the Sales Plan above, in recent weeks a number of our Building Partners have chosen lots for their show homes and in the case of Ultimate Builders, already have clients lined up for Home & Land packages. We are in negotiations on further lots, so please watch this space, and get in quick to secure your lot!   

Please visit our website for our latest Sales Plan, further information and links to our Building Partners: https://www.strathmorepark.co.nz/building-partners

SOUTH WAIKATO - SPACE TO GROW

A body of water with trees and a hill in the backgroundAI-generated content may be incorrect.

 

A person walking on a wooden path by a riverAI-generated content may be incorrect.

South Waikato is the perfect place for a great life, with wide open spaces, affordable housing, plenty of jobs and welcoming communities. The perfect place for business, big and small. With plenty of land and commercial properties at a fraction of big-city prices. Time to make the move?

For further information on the South Waikato region please visit: https://swnz.co/

CONTRACTOR COMMENTS – FROM ROUSE CONTRACTORS LTD (RCL)

As you can see from the recently taken aerial image, solid progress is being made with the earthworks, and the development is really starting to take shape. This is despite several significant weather events in recent weeks, which the dedicated team at RCL has been actively managing — both from an environmental standpoint and in terms of trying to maintain our programme and development timeframes. 

An aerial view of a construction siteAI-generated content may be incorrect.

KEY PROGRESS UPDATES:

Environmental Management - Waikato Regional Council has been in weekly contact and is very happy with the work RCL has completed to manage environmental controls, particularly during the recent rain events.

Programme Update - Due to the impact of recent wet weather, the overall programme has been pushed out by 8 days. RCL is actively working to mitigate any further delays and maintain momentum across all areas of the development.

Strathmore Park Playing Fields - Stormwater works have been completed, and grass strike has occurred. The dry pond performed well during recent rain events, effectively managing runoff in this flood-prone area.

Building Platforms - All building platforms in Stage 1 (northern boundary) have been completed, topsoiled, and have achieved grass strike. Approximately 50% of the platforms in Stages 2 and 3 have also reached this stage.

Roading and Stormwater Infrastructure - Subgrade formation is nearing completion across all Stages. The importation of roading metal has begun, and road formation of Stage 1 is expected to be completed within the next couple of weeks. In addition, stormwater infrastructure — including all roading cesspits — has been completed in Stage 1. These milestones significantly improve surface water management and will make ongoing environmental management across the site much easier, especially during wet weather.

Wastewater Infrastructure - Works in Stage 1 have been completed. Construction has now commenced in Stages 2 and 3. Connections to the Football Club and public toilet facilities are operating effectively.

Western Area Expansion - Excavation continues westward over the rise, and material is still being placed to build up this area.

CONTACTS FOR STRATHMORE PARK SUBDIVISON

Rouse Contractors Ltd – Managing the Earthworks & Civil Construction on the site.

Chris McGeough, Cell: 027 288 6165 | Email: chris@matangaprojects.co.nz 

Or, Clyde Rouse, Cell: 027 291 2898 | Email: clyderouse1@gmail.com

S&L Land Specialists – Civil Engineering & Land Development – manage the development.

Roger Harding, Cell: 022 350 2164 | Email: rharding@sllp.co.nz 

Or, Chris Hammerich, Cell: 022 311 0185 | Email: chammerich@sllp.co.nz

Subdivision SalesStage 1 selling now – Steven Farrant, Sales Director, Strathmore Park.

Steven Farrant, Sales Director, Cell 022 121 1897 | Email: steven@sllp.co.nz  

Please visit our website: https://www.strathmorepark.co.nz/

STAY CONNECTED

A screenshot of a computer screenAI-generated content may be incorrect.

To receive future issues of the Strathmore Park Newsletter, please visit our website and Register your Interest on our contact us page: strathmorepark.co.nz/contact-us